In consultation with the STOWA supervision committee for MBR projects, the Rhine and IJssel Water Board and DHV drew up a research programme containing the following objectives:

  1. demonstrating the technical feasibility of scaling up the MBR technology;
  2. demonstrating the stability of the operational management;
  3. determining the technical results, subdivided into pre-treatment, biological operation and membranes;
  4. investigating the need for redundancy;
  5. optimising process management;
  6. evaluating the design (based on items 1 to 5 inclusive);
  7. comparing the costs of the MBR plant with the costs of a conventional plant.

 

 